Schedule
§As a whole, MDT is a “+2” project, but should probably be “+3” or “+4” based on its dependencies
§
§M3 met on November 16
§
§M4 slipped from January 4 to January 22
§
§M5 met on February 23
§
§M6 slipped from April 6 to April 10
§
§M7 slipped from May 18 to May 24
Discuss the initial schedule and any changes to the schedule over the course of the release, i.e., what the project team achieved. Discuss whether milestones were met or slipped. Reason: The community relies on consistent schedules from Eclipse so that projects and products can plan for the correct dependencies.